Material inspection request (MIR): the two-step site receipt that keeps bad material out of stock

Material inspection request (MIR): the two-step site receipt that keeps bad material out of stock

Published By

Umar Shariff
Construction/Contracting
Nov 21, 2026

In short: A material inspection request (MIR) is how a Saudi site asks for, and records, the technical check on material that has just arrived. It works best as the second of two signatures. The storekeeper first confirms the quantity against the purchase order, even for ready-mix concrete. The project manager then confirms the material matches the specification the consultant approved in the submittal. Only after both signatures does the delivery become stock. A rejection becomes a return against that receipt, a part delivery keeps the purchase order open, and every receipt records the building, floor and zone. Below: the two steps, the MIR fields, a worked porcelain example, a register with ageing, a monthly count and a free MIR and site receipt register kit.

It is Sunday, 7:10 in the morning, on a residential tower site in north Riyadh. Two ready-mix trucks are queuing at the gate, a lorry of porcelain tiles is parked behind them, and the storekeeper has one pen. He signs the concrete tickets, counts the porcelain boxes against the delivery note and signs that too. By Wednesday the supplier's invoice is with finance, and finance pays what the delivery note says. On Thursday the site engineer opens the boxes on the eighth floor and finds the tiles are a different series from the sample the consultant approved.

Nobody on that site was careless. The storekeeper did his job, which was counting. What was missing was a second, separate signature that says "this is the right material", and a rule that a delivery is not stock until both signatures are on it. This article sets out that rule as a Saudi general contractor runs it across several sites at once.

Why does a delivery need two signatures before it becomes stock?

Most site stores mix two different questions into one signature: "did the quantity arrive?" and "is it what we ordered and the consultant approved?" When one person answers both on a busy morning, these things happen:

  • Counted but wrong. The quantity is right and the specification is not: a 35 MPa mix instead of 50 MPa, a different tile series, cable from an unapproved brand.
  • The delivery note becomes acceptance. A signed delivery note reaches finance and is treated as "received in good order", so the invoice is paid in full.
  • Rejected material sits in stock. Nobody records the rejection, so the system still shows the material as available and someone issues it.
  • Part deliveries close the order. The PO is marked complete after the first lorry, and the balance is never chased.
  • Nobody knows where it went. Material arrives "at site" when the site has three buildings and twenty floors.
  • Concrete is never received at all. It is poured straight from the truck, so it never appears as a receipt, and its cost reaches the project only when the invoice does.
The two-step site receipt: the storekeeper confirms quantity against the PO, the project manager confirms the specification against the approved submittal, then the delivery becomes stock or is returned against the receipt
A delivery becomes stock only after the quantity and technical signatures

The fix is simple to say. Every delivery gets two signatures, from two people, in a fixed order. The storekeeper signs for quantity. The project manager signs for the technical check. Stock moves only after the second signature.

What is a material inspection request (MIR) in construction?

An MIR is a short form raised when material reaches site, asking the person responsible for the technical check to inspect it against what was approved. On many Saudi projects the consultant's inspector attends as well, as the contract and the inspection and test plan require. Inside the contractor, the technical decision in this method belongs to the project manager.

The MIR does not approve the material in principle. That happened earlier, in the material submittal, when the consultant approved the product, its data sheet and its sample before procurement chose a supplier. The MIR checks that what arrived is the thing that was approved.

DocumentWhenQuestion it answersWho decides
Material submittalBefore the supplier is chosenIs this product acceptable for the job?Consultant
Purchase orderAfter the submittal is approvedWhat, how much, by when, to which zone?Procurement, cost control
Site receipt (step 1)At the gateDid the ordered quantity arrive?Storekeeper
MIR (step 2)Within a set time after receiptIs this the approved material, in good condition?Project manager, consultant where required
Work inspection requestAfter the material is installedIs the finished work ready to cover?Consultant

If the installed work is your next question, our guide to the work inspection request (WIR) covers that later step.

Step one: how should the storekeeper receive quantity?

The storekeeper's job is to count; judging the specification comes later. He checks the delivery against the purchase order and records what came, where it went, and what is still due.

  • Match the PO, not only the delivery note. The PO line, the item and the unit must match. A delivery with no PO is held at the gate until procurement confirms it.
  • Count everything, including concrete. For ready-mix, the storekeeper signs each truck ticket with its volume and pour location. Concrete is received like any other material, then issued straight to the pour.
  • Record the location. Every receipt carries building, floor and zone. Without them, the monthly count cannot find the material and the cost cannot follow the work.
  • Keep part deliveries open. If 850 of 900 metres of cable tray arrived, the receipt says 850 and the PO keeps 50 open.
  • Put it in "awaiting inspection". The delivery is on site but not yet stock. Mark the area or tag the pallets so nobody issues it.

The storekeeper then raises the MIR, or the receipt raises it for him. Either way, the MIR number goes on the receipt and the receipt number goes on the MIR, so each can always be found from the other.

Step two: what does the technical check look at?

The project manager, with the consultant's inspector where the contract asks for it, checks the delivery against the approved submittal. A good MIR form asks the same questions every time:

The fields of a material inspection request: approved submittal reference, specification and grade, brand and model, certificates and test reports, condition and storage, and the result with comments
Six things every material inspection request checks
  • Approved submittal reference. Which approval this delivery is checked against.
  • Specification and grade. Concrete strength class, steel grade, tile series and size, cable size and type.
  • Brand, model and origin. The same manufacturer and model the consultant approved.
  • Certificates and tests. Mill certificates, the supplier's test reports, and any samples to be taken, such as concrete cubes.
  • Condition and storage. Damage, expiry dates on chemicals and adhesives, and storage that will keep the material good until it is used.
  • Result. Approved, approved with comments, or rejected, with the reason written down and the inspector's name and date.

Set a time limit for the check and measure it. Two working days after receipt is a reasonable starting point; your project may need less for concrete samples and allow more for complex equipment. Count working days on a Sunday-to-Thursday week. An MIR that waits a week leaves the site with two bad choices: install unchecked material or stop work.

What happens to a rejected delivery?

A rejection is not a note in a WhatsApp group. It becomes a return against the receipt it came on, so the quantity leaves "awaiting inspection" and never reaches stock, the supplier's invoice can be matched to the accepted quantity only, and the PO line stays open for the replacement.

A worked example from a residential tower:

StepQuantity (m²)
PO line: porcelain tiles 60 × 120, phased delivery2,000
First delivery received by the storekeeper (Building A, floor 8, zone east)1,000
MIR result: 60 m² chipped, the rest matches the approved sampleapproved with comments
Returned against the receipt60
Accepted into stock940
Still open on the PO for the next deliveries1,060
Quantity the supplier can invoice for this delivery940
Worked porcelain example: 2,000 square metres on the PO, 1,000 delivered, 60 rejected and returned against the receipt, 940 accepted into stock, 1,060 still open on the purchase order
A partial rejection: what is accepted, returned and still open

Three rules make this work. The return quotes the receipt and MIR numbers. The accepted quantity, not the delivered quantity, is what finance can pay. And the open balance stays on the PO until the last good delivery arrives, or until procurement formally closes the line.

Why does the purchase order carry a delivery schedule by zone?

The receipt is only as good as the order behind it. The Saudi contractor in our example now writes the delivery schedule into the PO by zone and date. As one of its managers put it in a requirements meeting, the schedule is there "so as a legal document I can say you're late." Each receipt is then compared with a dated line, and late or short deliveries become the basis for delay penalties instead of an argument.

This matters most for long-lead items. HVAC equipment may need a PO four to six months ahead with phased deliveries; most other materials are ordered within a week of the consultant's approval. A dated schedule, receipts against it and an MIR on each delivery are what let you prove which deliveries were late.

How do you number and track MIRs in one register?

Give every MIR a number that tells you the project and the sequence, for example TWR2-MIR-0147. Keep one register per project with a row for every delivery, and four columns that matter more than the rest:

  • Status: awaiting inspection, approved, approved with comments, rejected.
  • Ageing: working days from receipt to the technical decision, or to today while it waits.
  • Overdue flag: anything past your time limit.
  • PO balance: what is still open on that PO line after accepted quantities.
An MIR register by status and ageing: awaiting inspection, approved, approved with comments and rejected, with overdue items past two working days flagged in red
Read the MIR register by status and age every morning

The site manager reads the overdue list every morning, the project manager clears it, and procurement reads the rejected list every week to decide which supplier to speak to. If the same supplier appears on the rejected list three times in a month, that calls for a conversation with the supplier.

Why count every site store every month?

Every site is a store, and a store you never count drifts. Once a month, count what is physically on site by building, floor and zone and compare it with the system. Then look at one more number: how long has each item been sitting there?

  • Idle for two weeks: ask why. The work may have moved, or the material may be in the wrong zone.
  • Idle for three weeks: act. It may be damaged, surplus, ordered too early or waiting for a decision.
The monthly site store count: compare counted with system quantity by building, floor and zone, and flag any item idle for two weeks for a question and three weeks for action
Monthly count: a variance and an idle-days flag for every item

Equipment issued to people or subcontractors is tracked as custody, so the count can name who holds each item. The idle flag is often more useful than the variance: material that arrived early ties up cash and gets damaged long before anyone needs it.

How can you start in 30 days?

  • Week 1: agree the two signatures and who gives them on each site. Print the MIR form. Mark an "awaiting inspection" area in every store.
  • Week 2: start the register on one site. Every delivery gets a receipt with building, floor and zone, and an MIR number.
  • Week 3: route rejections as returns against the receipt and make sure finance pays the accepted quantity only.
  • Week 4: run the first monthly count, read the idle list, and roll the method out to the next site.

Download the free MIR and site receipt register

The kit gives you everything above, ready to use on Monday:

  • Excel register: a Start here sheet, Settings (project, buildings, floors, zones, your inspection time limit and holidays), a printable MIR form, the receipt and MIR register with status, working-day ageing, overdue flags and PO balance, and a monthly count sheet that flags items idle for two and three weeks.
  • PDF guide: the two-step method, the MIR fields, the porcelain example, the daily and monthly routine, the 30-day start and a blank MIR form to print.

Where does HAL Contracting fit?

A register works on one site. Across several sites, the receipt, the PO and the invoice need to live in one system. In HAL Contracting, site requests are raised against the BOQ, the item receipt is posted against the purchase order, and purchase order reconciliation shows what was ordered, received, invoiced and still pending for every PO and project. The vendor invoice is capped at the received quantity, and purchase returns and debit notes are raised against a receipt or invoice. Approval workflows with as many levels as you need can sit on any transaction. HAL's Quality Control page describes receiving inspections defined in quality control plans for inventory operations; ask HAL how that fits your site receipts. Where a site admin pays a supplier from company cash they hold, HAL's employee-custody vendor payment clears that advance against the supplier's bill, with both the vendor and the employee recorded correctly. See HAL pricing for the plans.

Related reading: paying suppliers from site petty cash, BOQ budget control for purchase requests and splitting supply and install subcontracts.

Frequently asked questions

What is a material inspection request in construction?

A material inspection request (MIR) is the form raised when material arrives on site, asking for a technical check that the delivery matches the material the consultant approved in the submittal. It records the specification, brand, certificates, condition and the result: approved, approved with comments or rejected.

What is the difference between an MIR and a material submittal?

The material submittal comes first and asks the consultant to approve a product before the supplier is chosen. The MIR comes later, when that product is delivered, and checks that what arrived is the approved product in good condition.

Who signs a material inspection request?

In the two-step method, the storekeeper signs the receipt for quantity and the project manager signs the MIR for the technical check. Where the contract or the inspection and test plan requires it, the consultant's inspector also inspects and signs.

Should concrete be received by the storekeeper?

Yes. The storekeeper signs each ready-mix ticket with its volume and pour location, so concrete is received like any other material and its cost follows the pour. The technical side, such as the mix class and cube samples, goes on the MIR.

What happens when material is rejected on site?

The rejected quantity is returned against the receipt it arrived on. It never becomes stock, the supplier can invoice only the accepted quantity, and the purchase order line stays open for the replacement delivery.

How long should a material inspection take?

Set a limit and measure it. Two working days from receipt, counted on a Sunday-to-Thursday week, is a reasonable starting point. The register's ageing column and overdue flag show which deliveries are waiting too long.

Umar Shariff