Monthly progress claims (IPC) and retention in Saudi Arabia: a worked example

Monthly progress claims (IPC) and retention in Saudi Arabia: a worked example

Published By

Umar Shariff
Construction/Contracting
Nov 21, 2026

In short: A monthly progress claim (also called an interim payment certificate, or IPC) is how a Saudi contractor gets paid for the work done each month. Site records the quantity done on every BOQ line, the consultant and owner certify it, finance issues a tax invoice with 15% VAT, and the owner deducts retention and recovers part of the advance before paying. This article walks through one claim on a SAR 43M project with real, rounded numbers, shows how retention released in one or two portions changes your cash, and gives you a free IPC and retention calculator in Excel.

It is the 22nd of the month. The quantity surveyor is chasing three site engineers for their measurements, the consultant has sent back last month's claim with comments on the blockwork, and finance is asking which figure goes on the tax invoice. Next month someone in management will ask how much retention the owner is holding across all projects, and the answer will take a day to build.

The progress claim is the most important document a contractor produces every month. It decides revenue, VAT and cash in one go. This guide follows one claim from site to bank on a real Saudi project, rounded and anonymised, so you can check your own cycle against it.

What is a monthly progress claim, and how does the cycle run?

A progress claim is the contractor's request for payment for the work done in a period, usually one month. Once the consultant and the owner approve it, it becomes a certificate (the "interim payment certificate", or IPC in FIDIC-style contracts; most Saudi site teams simply call it the مستخلص). The contractor then issues a tax invoice for the certified amount.

The cycle has five steps, and each one has an owner.

The monthly progress claim cycle for a Saudi contractor: measure work done per BOQ line, submit the claim with attachments, consultant and owner certify, finance issues the tax invoice with VAT, retention and advance recovery, then collect and track due and overdue
The monthly progress claim cycle, from site measurement to cash
StepWhoWhat leaves the deskTypical timing
1. MeasureSite engineer, then QSQuantity done per BOQ line, with measurement sheets and photosCut-off day, for example the 25th
2. SubmitQS or commercial managerThe claim: quantities, values, previous and cumulative totalsWithin a few working days of cut-off
3. CertifyConsultant, then ownerCertified quantities and value, often with changesAs the contract says, often two to four weeks
4. InvoiceFinanceTax invoice on the certified value, with VAT, retention and advance recoveryRight after certification
5. CollectFinanceReceipt matched to the invoice; retention moved to its own balanceThe payment term, for example 10 days after certification

The contract sets the cut-off day, who certifies, how long they have and when payment is due. Write those four facts on the first page of your claim file, because every late payment argument comes back to them.

How do you measure work done per BOQ line?

Every claim starts as a progress form: one row per BOQ or budget line, with the quantity done this period. The best forms we have seen on Saudi sites separate two quantities that most templates merge.

  • Quantity done is what site has physically completed this period.
  • Quantity to invoice is what you are claiming now. It can be lower than the quantity done (a zone not yet inspected, a measurement sheet still unsigned), never higher than the quantity done and not yet invoiced.

A Saudi general contractor building multi-storey blocks runs its monthly form with three rules, and they are worth copying:

  1. Quantity to invoice cannot exceed done-but-not-invoiced. If 4,000 m² of blockwork is done and 3,500 m² is invoiced, the other 500 m² waits for next month with a reason.
  2. Periods cannot overlap. Each claim covers a from-date and a to-date that start where the previous one ended. Overlaps are how the same quantity gets claimed twice.
  3. An attachment is required on every line. No measurement sheet, inspection request or photo, no claim line.

Expect the consultant to certify a slightly different figure from the one you submitted. On that contractor's projects, site progress and certification differed by up to ±5% in a month. That is normal. What matters is that you can show the difference line by line and carry the uncertified quantity into the next claim instead of losing it.

How are retention, advance recovery and VAT calculated on a claim?

Here is claim 9 on a SAR 43M (ex-VAT) building contract. The owner paid a 10% advance (SAR 4.3M) at the start, and the contractor issued a tax invoice with VAT when it was received. The contract says the advance is recovered at 10% of each claim and retention is 10% of the gross value certified. Your percentages will differ; the order of the calculation usually does not.

LineAmount (SAR)How it is worked out
Submitted this period2,360,000From the progress form
Certified this period2,300,000Consultant's figure, 2.5% below submitted
Less advance recovery (10%)−230,000VAT was already paid on the advance when it was received
Taxable value2,070,000Certified minus advance recovered
VAT (15%)310,500On the taxable value
Invoice total incl. VAT2,380,500
Less retention (10% of certified)−230,000Withheld by the owner; VAT is still due on it
Amount payable2,150,500Due 10 days after certification
Progress claim calculation on a SAR 2.3M certified claim: advance recovery of 230,000, taxable value 2,070,000, VAT of 310,500, retention of 230,000 and 2,150,500 payable
One certified claim, from gross value to the amount the owner pays

Two VAT points catch finance teams out, and both come from ZATCA's VAT guideline for the contracting sector (second issue, May 2026):

  • Retention does not reduce the VAT. When you invoice the full certified amount, VAT is due on all of it, even though the owner keeps part as retention. ZATCA's own example: a contractor invoices SAR 5M plus SAR 750,000 VAT, the owner withholds 6%, and the contractor still declares the full SAR 750,000. When the retention is paid later, there is no further VAT to declare.
  • VAT on the advance is paid when the advance arrives. So each later claim deducts the advance recovered before working out VAT, otherwise you charge VAT twice on the same money.

Contracts with government entities can have special date-of-supply rules, so check those separately. The retention invoice format article covers the invoice layout in detail.

When is retention released: in one portion or two?

Retention is your money, held as a guarantee. On this contract, 10% retention on SAR 43M means SAR 4.3M sits with the owner by the final claim. How it comes back depends on the contract.

  • One portion. Most owners release all retention after 12 months; release is often tied to completion and the defects liability period, so check your contract.
  • Two portions. Some owners release half at 6 months and the other half at 12. On this contract that would be SAR 2.15M back six months earlier.
Retention release timeline on a SAR 43M contract with 10% retention: SAR 4.3M held at the final claim, released in one portion at 12 months or in two portions of 2.15M at 6 and 12 months
Retention released in one portion or two: what it does to your cash

Retention fails quietly in three ways: nobody diarises the release date, nobody chases the release document, and nobody notices that the owner has released one portion and not the other. Keep a retention balance per project, split by release date, and review it every month with the receivables. If you also hold retention from your own subcontractors, track it the same way, in the other direction.

What should the monthly claim dashboard show?

The same general contractor reads one dashboard per project every month. These are its real figures, rounded:

MeasureFigure
Contract value (ex-VAT)SAR 43M
Certified to dateSAR 17M
CollectedSAR 14M
ReceivableSAR 3M
Payment term10 days after certification
Physical progress, actual vs planned54% vs 53%
Cash in vs cash outSAR 14M vs SAR 13M
Target margin10–20%
Monthly progress claim dashboard for a SAR 43M Saudi project: 17M certified, 14M collected, 3M receivable, progress 54% against 53% planned, due and overdue shown separately
A real project's claim dashboard, rounded: certified, collected, receivable and progress

Three things on it are worth noticing.

  • Due and overdue are separate lines. A claim certified on 12 October is due on 22 October. Before that date it is simply due; the day after, it is overdue and someone calls. One "receivables" number hides the difference.
  • Physical progress and certified value tell different stories. 54% progress against SAR 17M certified (about 40% of the contract) is a gap worth one sentence every month. It can be work done and not yet claimed, claims waiting for certification, or a programme that weights activities differently from BOQ value. Each needs a different action.
  • Cash in only just covers cash out. With SAR 14M in and SAR 13M out, one late certificate can turn the project's cash negative. Cost control also saw commitments finance did not, such as retention payable to subcontractors and steel bought on two to three months' credit. Put those on the same page.

What delays payment, and how do you track due against overdue?

Most late payments start inside the contractor's own office. Check these before blaming the owner:

  • Missing or late attachments. A line with no measurement sheet is the easiest one for a consultant to strike out.
  • Quantities nobody can trace. When site, QS and the claim disagree, certification waits for the argument to finish.
  • Late submission. A claim sent a week after cut-off is certified a week later, and paid a week later.
  • An invoice that does not match the certificate. Different amount, missing client PO number or wrong VAT treatment, and the owner's accounts team sends it back.
  • Unapproved variations in the claim. Claim them separately once instructed and priced; mixing them in holds up the whole certificate.

Then track every claim against its due date. Due date equals certification date plus the payment term. Count working days in your follow-up (Sunday to Thursday), and agree in the contract what happens when a due date falls on a Friday or Saturday. Each week, list overdue claims by days overdue, with a named person chasing each one.

Which accounting entries does each step create?

Using claim 9 above (simplified; your chart of accounts will differ):

EventDebit (SAR)Credit (SAR)
Advance received at the startBank 4,945,000Advance from client 4,300,000; Output VAT 645,000
Claim 9 certified and invoicedClient receivable 2,150,500; Retention receivable 230,000; Advance from client 230,000Contract revenue 2,300,000; Output VAT 310,500
Payment receivedBank 2,150,500Client receivable 2,150,500
Retention released after 12 monthsBankRetention receivable (no VAT)

Many contractors recognise revenue on the percentage of completion rather than on certification, so agree the method with your auditor. Our guide to retention in construction explains the retention entries and their effect on cash flow.

Download the free IPC and retention calculator

The IPC and retention calculator (Excel, with a PDF guide) runs the cycle above on your own contract:

  • Settings for contract value, VAT, advance, recovery rate, retention rate, retention portions and payment term
  • Progress form per BOQ line with quantity done, quantity to invoice, the no-overlap and attachment checks
  • Claim sheet per period: certified vs submitted (flagged above ±5%), advance recovery capped at the advance balance, VAT, retention, amount payable, due date, due or overdue, days overdue
  • Retention schedule by portion and release date
  • Dashboard with certified, collected, receivable, retention held and advance still to recover
  • The PDF guide with the cycle, the worked claim, a month-end checklist and a printable claim summary

The example rows use the SAR 43M contract from this article, so you can see every formula working before you type over them.

Running progress claims in HAL Contracting

When claims run across several projects, the spreadsheet becomes the bottleneck. In HAL Contracting you pick the project and HAL brings its contract terms. Enter the work done, and the progress claim deducts retention by percentage or amount, recovers the client's advance together with its VAT, and takes off penalties or other deductions, each to its own ledger. Retention is released later with a retention invoice for the same project. The claims register shows client approval date, ZATCA status, balance, retention held and advance recovered for every claim, and claims are issued with ZATCA Phase 2 e-invoicing. Customer payments are applied against open invoices in HAL Accounting. See HAL pricing for what it costs.

Related reading: variation orders on the BOQ, splitting supply and install subcontracts and job costing: actual vs estimated cost.

Frequently asked questions

What is the difference between a progress claim and an IPC?

The progress claim is what the contractor submits for the work done in a period. Once the consultant and owner approve it, it becomes the interim payment certificate (IPC). The contractor then issues the tax invoice for the certified amount, with VAT, retention and advance recovery shown on it.

Is VAT charged on retention in Saudi Arabia?

Yes, when you invoice the full certified amount. ZATCA's contracting guideline says VAT is due on the whole invoiced amount even if the owner withholds part as retention, and no further VAT is declared when the retention is paid later. Contracts with government entities can follow special rules, so check those separately.

How is the advance recovered on each claim?

The contract sets a recovery rate, often a fixed percentage of each certified claim, until the advance is fully recovered. Because VAT was already paid when the advance was received, each claim deducts the advance recovered before calculating VAT, so the same money is not taxed twice.

When is retention released?

Most Saudi owners release retention after 12 months; release is often tied to completion and the defects liability period, so check your contract. Some release it in two portions, typically half at 6 months and half at 12. Track each portion with its own release date and balance.

Why does the certified amount differ from what we submitted?

The consultant measures independently and may disagree on quantities, quality or attachments. A difference of a few percent is common; one contractor saw up to ±5% in a month. Show the difference line by line and carry any uncertified quantity into the next claim.

When does a progress claim become overdue?

On the day after its due date, which is the certification date plus the payment term in the contract, for example 10 days. Track due and overdue claims separately and give every overdue claim a named person to chase it.

Umar Shariff