Supply and install subcontracts: why Saudi contractors split them into supply and works

Supply and install subcontracts: why Saudi contractors split them into supply and works

Published By

Umar Shariff
Construction/Contracting
Nov 21, 2026

In short: When every subcontract invoice says supply and install, a Saudi contractor cannot show which materials it supplied itself, and its contractor-classification profile can look as if it subcontracted whole projects. The fix is to split each subcontract into a supply invoice and a works certificate that both reconcile to the BOQ quantity, for example 1,000 m² of marble supplied and 1,000 m² installed, with retention and advance recovery tracked per subcontractor. This article shows the split with a marble example, the two ways to do it, how to handle the subcontractor who wants to keep his supply margin, and a free Excel template.

A Saudi general contractor went through a contractor-classification review. The reviewer asked a simple question: on this building, what did you supply yourselves and what did you subcontract? Finance pulled the subcontract invoices. Marble, porcelain, gypsum, HVAC, aluminium: every one of them said "supply & install". On paper, the company had subcontracted the building. In reality it had bought, approved, stored and paid for most of the materials through its own procurement and site teams.

Nobody had done anything wrong. The invoices simply did not say what had happened. This guide shows how to make them say it.

Why does "supply and install" on every invoice hurt a contractor?

A supply-and-install subcontract is a perfectly normal agreement. The trouble starts when the invoice is one line with one rate, month after month.

Six problems with supply and install on every subcontract invoice: the classification profile looks fully subcontracted, own supply cannot be shown, material prices cannot be compared, the BOQ line build-up is lost, retention and advance sit on a blended figure, and site receipts do not match invoices
Why a single supply-and-install line on every subcontract invoice hurts the contractor
  • Your profile looks like full subcontracting. In a classification review or a prequalification, a company that cannot show its own supply looks like a manager of subcontractors.
  • You cannot show what you supplied. The material was approved by the consultant, received by your storekeeper and paid by your finance team, and none of that appears on the invoice.
  • You cannot compare material prices. Marble from one subcontractor at a blended SAR 120/m² tells you nothing about the material price on your next tender.
  • The BOQ line build-up is lost. A good budget line splits into materials, labour, subcontractor, tools and other costs. A single blended rate puts everything under "subcontractor".
  • Retention and advance sit on a blended number. You hold 10% of a figure that mixes material delivered last month with installation that may still have defects.
  • Site receipts do not match invoices. Your storekeeper signs for 600 m² of marble; the invoice bills 450 m² installed. Two different quantities, one document.

How do you split a subcontract into supply and works?

Every subcontract gets two documents: a supply invoice for material delivered to site, priced per unit of material, and a works certificate for work installed, measured and priced per unit of installation. Both carry the same BOQ line, and both add up to the BOQ quantity.

Take marble flooring on a BOQ line of 1,000 m². In the market a split like this is roughly SAR 70/m² for supply and SAR 50/m² for installation.

Before: one invoiceAfter: two documents
Document"Supply & install marble"Supply invoice + works certificate
Quantity1,000 m²1,000 m² supplied + 1,000 m² installed
RateSAR 120/m²SAR 70/m² supply + SAR 50/m² install
ValueSAR 120,000SAR 70,000 + SAR 50,000
Shows as subcontractedSAR 120,000 (100%)SAR 50,000 (about 42%)
Shows as own supplyNothingSAR 70,000 (about 58%)
Supply and install marble split on a 1,000 m² BOQ line: one invoice of SAR 120,000 before, a SAR 70,000 supply invoice and a SAR 50,000 works certificate after, so the subcontracted share falls from 100% to about 42%
The marble example: one SAR 120,000 invoice becomes SAR 70,000 supply and SAR 50,000 works

The total does not change. What changes is the record: the material is on a document that matches your site receipt, and only the installation is subcontracted work.

How do the supply and works documents reconcile to the BOQ?

The rule is simple, and worth writing into every subcontract: the sum of the supply documents equals the BOQ quantity, and so does the sum of the works documents. A BOQ line of 1,000 m² can be covered by several documents from more than one company. On that general contractor's sites one BOQ line could have four or five subcontractors.

DocumentSubcontractorMonthSupplied (m²)Installed (m²)
Supply invoiceMarble subcontractor1600
Works certificateMarble subcontractor1450
Supply invoiceMarble subcontractor2400
Works certificateMarble subcontractor2350
Works certificateMarble subcontractor3200
Total against BOQ 1,000 m²1,0001,000
BOQ reconciliation for a supply and install split: 1,000 m² of marble on the BOQ equals 600 plus 400 m² on supply invoices and 450 plus 350 plus 200 m² on works certificates, with 200 m² on site but not installed at month 2
BOQ 1,000 m² equals the sum of the supply documents and the sum of the works documents

At the end of month 2 the line reads 1,000 m² supplied and 800 m² installed. The 200 m² difference is material on site, which your storekeeper should be able to count. If supplied ever exceeds the BOQ quantity, or installed exceeds supplied, someone has to explain it before the next payment.

Two habits make this work. The supply invoice is matched to your site receipt, quantity first and then a technical check by the project manager against the approved material, with building, floor and zone on the receipt. The works certificate is matched to a measurement, in the same way you measure your own claim to the owner.

Option 1 or option 2: buy the material yourself, or two invoices per subcontractor?

There are two ways to get there, and many contractors use both on the same project.

Option 1: you buy, they installOption 2: two documents per subcontractor
How it worksYou issue the PO to the manufacturer or distributor; the subcontract is install-onlyThe subcontractor supplies and installs, but bills supply and works separately
Material on your POYes, at your negotiated priceNo, on the subcontractor's invoice
Who carries breakage and wastageYou, unless the install-only subcontract says otherwiseThe subcontractor
AdminMore POs, deliveries and stock to manageTwo documents a month per subcontractor
Works best forHigh-value, long-lead or bulk items: porcelain, marble, HVAC unitsSpecialist items where the subcontractor's supply chain matters
Two ways to split supply and install subcontracts: option 1, the contractor buys the material and hires install-only, with material on its own PO but more stock to manage; option 2, the subcontractor issues a supply invoice and a works certificate, keeping supply risk with the subcontractor
Option 1 or option 2: who buys the material, and who carries the risk

Option 1 also lets you split one material across sources. That general contractor bought 20,000 m² of porcelain as two POs, 15,000 m² from the manufacturer and 5,000 m² from a distributor, and hired installation separately. For long-lead items such as HVAC, the PO may go out four to six months ahead with phased deliveries, which is easier to control when the PO is yours.

Whichever option you choose, keep one rule from the vendor master: no VAT number and commercial registration on file, no payment. Both documents are tax invoices with 15% VAT, and your input VAT depends on them being right.

How do retention and advance recovery work per subcontractor?

Each subcontract carries its own retention and advance terms, and once you split, you apply them per document. In this example the marble subcontractor received a SAR 12,000 advance (10% of SAR 120,000), recovered at 10% of every document, with 10% retention on works certificates only.

DocumentValueAdvance recoveryVAT 15%RetentionPayable
Supply invoice, 600 m² × 7042,000−4,2005,670043,470
Works certificate, 450 m² × 5022,500−2,2503,037.50−2,25021,037.50
Supply invoice, 400 m² × 7028,000−2,8003,780028,980
Works certificate, 350 m² × 5017,500−1,7502,362.50−1,75016,362.50
Works certificate, 200 m² × 5010,000−1,0001,350−1,0009,350
Total120,000−12,00016,200−5,000119,200

The advance is fully recovered by the last certificate, and SAR 5,000 of retention is held against the installation, which is where defects show up. Some agreements also hold retention on supply; the template lets you set a separate rate for each.

Retention you hold from subcontractors is money you owe later. Cost control usually sees it as a commitment before finance does, so put it on the same report as the retention your owner holds from you.

What about the subcontractor who wants to keep his supply margin?

Expect resistance. A subcontractor who buys marble at one price and bills it inside a blended rate earns a margin on the material. Splitting the invoice shows that margin, and option 1 can remove it.

  • Talk about the total first. You are asking for a different document, and the total per m² can stay the same.
  • Accept a fair handling margin on option 2. The subcontractor still sources, transports and stores the material, and that work is worth paying for.
  • Expect the install rate to move on option 1. Some subcontractors recover lost supply margin through a higher installation rate. Compare the full cost per m² before deciding.
  • Put the split in the tender documents. It is easier to agree before the price than after.
  • Start with the big lines. Marble, porcelain, HVAC and aluminium carry most of the value; do not split small lines just to be consistent.

Start in 30 days

WeekDo this
1List active subcontracts with a supply element. Mark which are already split.
2Pick the three highest-value lines. Agree option 1 or 2 with each subcontractor.
3Issue the first split documents and reconcile them to the BOQ and site receipts.
4Review the supply-vs-subcontracted profile per project with management.

Download the free subcontract supply/works split template

The subcontract supply/works split template (Excel, with a PDF guide) does the arithmetic:

  • Subcontract register with option, supply and install rates, retention rates for supply and works, advance and recovery rate
  • Documents log for supply invoices, works certificates, your own PO receipts and any unsplit invoices, with advance recovery capped at the advance balance, VAT, retention and payable
  • BOQ reconciliation per line: BOQ quantity, supplied, installed, material on site and a flag when documents do not add up
  • Supply vs subcontracted profile per project, before and after the split
  • Subcontractor statement with advance balance, retention held and amount still to pay
  • The PDF guide with the method, both options, a negotiation checklist and a printable split agreement schedule

Material and subcontract costs in HAL Contracting

In HAL Contracting, procurement sets the budget by activity and ties every BOQ item to it, and purchase requests from site are checked against the BOQ balance and the budget, then checked again at the purchase order. With "consume stock", material received on site is issued to the project at once, the vendor invoice is capped at the quantity received with any advance deducted automatically, and the purchase order reconciliation shows ordered, received, invoiced and pending for every PO, project and supplier. Vendor advances are capped at the PO value and settled against the invoice that follows. Our guide to subcontracting in procurement covers the wider process, and HAL pricing shows what it costs.

Related reading: monthly progress claims and retention, material inspection requests and two-step site receipt and BOQ budget control for purchase requests.

Frequently asked questions

What does supply and install mean in a subcontract?

The subcontractor provides the material and installs it, usually for one rate per unit. It is a normal arrangement, but when every invoice shows only that one rate, the contractor's records cannot show which materials it supplied and which work it subcontracted.

Why split a supply and install subcontract into two documents?

So that the supply invoice matches your site receipt and the works certificate matches a measurement, both against the same BOQ quantity. Your profile then shows the material as supply and only the installation as subcontracted work, which matters in a contractor-classification review or prequalification.

Does splitting change the price?

Not necessarily. In the marble example, SAR 120/m² becomes SAR 70/m² supply plus SAR 50/m² installation, the same total. Prices move only if you buy the material yourself or the subcontractor adjusts the install rate.

How do supply and works documents reconcile to the BOQ?

The sum of all supply documents for a BOQ line equals its quantity, and so does the sum of all works documents. If 1,000 m² is on the BOQ, the supply invoices add up to 1,000 m² and the works certificates add up to 1,000 m². Supplied minus installed is material on site.

How are retention and advance recovery applied after the split?

Per document, using the terms in each subcontract. A common setup recovers the advance at a fixed percentage of every document and holds retention on works certificates, where defects appear. Some agreements also hold retention on supply.

What if the subcontractor refuses to split?

Keep the total the same, allow a fair handling margin on supply, and write the split into the next tender. For high-value materials, buy them yourself and hire installation only.

Umar Shariff